June 21, 2024
Night-time runway rehabilitation at Graz Airport by the Kostmann team.
Several individual areas totaling 2500m² were renovated in several night shifts.
Due to the weather conditions, the dates had to be set and organized at short notice.
In order to ensure smooth operations and flight operations, the work was carried out outside of flight operations from 11:30 p.m. to 5:00 a.m.